Problem

The original railroad had been constructed on very soft soil and settling foundation which needed to be modernized and stabilized. This project also involved the construction of a new double railway track.

Solution

The total area of soil in need of stabilization was about 6500 m2, up to a depth of 3-4 m. The ALLU Soil Improvement system stabilized the area in one month. Binder used in this project was a mixture of cement (70%) and merit (30%).

Benefit

The complete ALLU Soil Improvement System stabilized the area cost and time efficiently, with no expensive haulage costs as there was no need for a mass exchange of material.